Date: 2023
Duration: 2 years
Value: 10M€
Location: Sultanate of Brunei Final
Client: TOTAL

Content: 2 compression trains using transformer, IGBT-type current filters with cooling, electromagnetic motor integrated into the compressor

Project Team Composition: Engineering (6 people), quality, purchaser (transformers and coolers for filter), cost control, filter sub-project (1PM, 5 technicians), motor sub-project (1PM, 5 engineers, 5-10 technicians), logistician.

Highlights: Management of delays caused by a flaw in the manufacturing method by the subcontractor of a new part designed to meet specific requirements of the final client. The supplier was unable to replicate the test part. Mitigation: we reduced the defect to a visual defect only, as the reliability and durability of the equipment had been ruled out as issues.

Claims Management: Contractual and legal review to reduce the penalties claimed by the client.